BSA Bird Island Treament Plant
»
|
|
|
|
|
Location |
Buffalo, NY |
Owner |
Buffalo Sewer Authority |
|
Contact Us |
|
|
|
click on an image to view a larger image |
|
|
Quackenbush was the prime mechanical contractor for this energy saving major pump replacement project at the Buffalo Sewer Authority's Bird Island Treatment Plant.
Six 28,000 gpm return activated pumps and four 1,400 gpm waste activated pumps were replaced while keeping the treatment plant operational.
Construction activity was split into two separate 30-day shutdowns. The largest pump assemblies weighed 21,000 lbs., with 30" connected piping and valves. General construction actitivies as well as extensive electrical changes were part of our responsibility.
The project was successfully and safely completed on time. |
|